Phase I: Task 1, General management reports. This Program Management Plan (PMP) has been prepared to identify and specify the administrative, technical and fiscal functions and controls that will be utilized during the Hawaii Deep Water Electrical Transmission Cable Demonstration Program (HDWC Program). The functions and controls have been developed and designed to assure that the overall Program work tasks are performed to the highest quality possible within the Program's organizational, time and budgetary constraints. Although this PMP has been prepared during the preliminary definitional phase of work (Phase I), it is intended for use by the Program Team as a working plan and directive during succeeding phases of work. As such, this PMP will be a dynamic document that will reflect changing Program conditions through revisions in design approach, scope and detail of Program elements as the project progresses.
Description
Keywords
engineering, Hawaii, Hawaii Deep Water Cable Program, Cables, Submarine--Hawaii, Electric power transmission--Hawaii, Electric lines--Hawaii, Electric cables, Underground electric lines--Hawaii
Citation
Chapman GA. 1982. Hawaii Deep Water Electrical Transmission Cable Demonstration Program: Phase I Task 1 general management reports. Honolulu (HI): State of Hawaii Department of Planning and Economic Development.
Extent
93 pages
Format
Geographic Location
Time Period
Related To
Table of Contents
Rights
Rights Holder
Local Contexts
Email libraryada-l@lists.hawaii.edu if you need this content in ADA-compliant format.